Jing Zheng Ban Fa〔2019〕No.10-Regulations on Approval Services for Simple and Low-Risk Construction Projects

  • 日期:2019-04-25 21-14
  • 来源:北京市规划和自然资源委员会
  • 字号:

 Regulations on Approval Services for

Simple and Low-Risk Construction Projects

 

Article 1 To formulate the regulations pursuant to the following provisions:

1. Regulations on Launching the Pilot Program of the Reform of the Approval System for Construction Projects (Guo Ban Fa [2018] No. 33)

2. Regulations on Comprehensively Launching the Reform of Examination and Approval System for Construction Projects (Guo Ban Fa [2019] No. 11)

Article 2 Simple and low-risk construction projects shall be in accordance with urban planning, with the constructed area above ground not exceeding 2,000 square meters, with the constructed area underground with no more than one floor not exceeding 1,000 square meters:

1. Office buildings shall meet the following requirements simultaneously:

(1) Without a chemical or biological laboratory.

(2) Not located at any of the following locations:

a. Where local municipal pipeline network is insufficient;

b. Pipeline access would destroy urban main road or expressway;

c. Adjacent to Chang'an Street or its extension line, or city central axis or its extension line, or Tian'anmen Square;

d. Scope for cultural relics protection;

e. Construction control zone for cultural relics;

f. Underground burial area for cultural relics;

g. Environmentally sensitive zone determined in the Detailed Implementation Rules of Beijing Municipality for Classified Management Catalogue of Environmental Impact Assessment of Construction Projects;

h. Within 30 meters of precious trees or old trees.

2. Commercial buildings shall meet the following requirements simultaneously:

(1) Not for selling flammable, explosive, toxic or hazardous materials;

(2) No emission of smoke or odor;

(3) Not located at any of the following locations:

a. Where local municipal pipeline network is insufficient;

b. Pipeline access would destroy urban main road or expressway;

c. Adjacent to Chang'an Street or its extension line, or city central axis and its extension line, or Tian'anmen Square;

d. Scope for cultural relics protection;

e. Construction control zone for cultural relics;

f. Underground burial area for cultural relics;

g. Environmentally sensitive zone determined in the Detailed Implementation Rules of Beijing Municipality for Classified Management Catalogue of Environmental Impact Assessment of Construction Projects;

h. Within 30 meters of precious trees or old trees.

3. Public service facilities shall meet the following conditions simultaneously:

(1) No kindergartens, schools, hospitals or homes for the elderly.

(2) Without a chemical or biological laboratory.

(3) Not located at any of the following locations:

a. Where local municipal pipeline network is insufficient;

b. Pipeline access would destroy urban main road or expressway;

c. Adjacent to Chang'an Street or its extension line, or city central axis or its extension line, or Tian'anmen Square;

d. Scope for cultural relics protection;

e. Construction control zone for cultural relics;

f. Underground burial area for cultural relics;

g. Environmentally sensitive zone determined in the Detailed Implementation Rules of Beijing Municipality for Classified Management Catalogue of Environmental Impact Assessment of Construction Projects;

h. Within 30 meters of precious trees or old trees.

4. Warehouses shall meet the following requirements simultaneously:

(1) Not for storing flammable, explosive, toxic, hazardous or dangerous materials.

(2) Not located at any of the following locations:

a. Where local municipal pipeline network is insufficient;

b. Pipeline access would destroy urban main road or expressway;

c. Central area of the city;

d. Adjacent to Chang'an Street or its extension line, or city central axis or its extension line;

e. Scope for cultural relics protection;

f. Construction control zone for cultural relics;

g. Underground burial area for cultural relics;

h. Environmentally sensitive zone determined in the Detailed Implementation Rules of Beijing Municipality for Classified Management Catalogue of Environmental Impact Assessment of Construction Projects;

i. Within 30 meters of precious trees or old trees.

5. Plants shall meet the following requirements simultaneously:

(1) Not for producing flammable, explosive, toxic, hazardous or dangerous materials.

(2) Not located at any of the following locations:

a. Where local municipal pipeline network is insufficient;

b. Pipeline access would destroy urban main road or expressway;

c. Central area of the city;

d. Adjacent to Chang'an Street or its extension line, or city central axis or its extension line;

e. Scope for cultural relics protection;

f. Construction control zone for cultural relics;

g. Underground burial area for cultural relics;

h. Environmentally sensitive zone determined in the Detailed Implementation Rules of Beijing Municipality for Classified Management Catalogue of Environmental Impact Assessment of Construction Projects;

i. Within 30 meters of precious trees or old trees.

Article 3 A “One-stop” service system deals exclusively with simple and low-risk construction projects.

No other permits or assessments or inspections or services need to be processed outside the “One-stop” service system.

District government departments are authorized to handle all permits and inspections.

Article 4 The cancellation of permits, assessments and inspections include but not limited to:

1.Various land use and planning conditions approvals;

2. Environmental evaluation;

3. Traffic impact assessment;

4. Water impact assessment;

5. Energy conservation evaluation;

6. Seismic safety evaluation;

7. Construction permits of civil defense basement and charge of transfer-construction cost;

8. Registering for direct contracting of design and construction;

9. Filing and publishing contractor information;

10. Building drawing review;

11. Completion inspection and acceptance of civil defense facilities;

12. Completion inspection and acceptance of traffic facilities;

13. Completion files acceptance;

14. Completion inspections and acceptances of water, power, gas, heat and other engineering facilities.

Article 5 To request and obtain the following permits and services with only one application form and one copy of documents:

1. Registering for the construction project;

2. Planning permit;

3. Lumbering permit;

4. Inquiry and request water and sewage connection.

Article 6 The time limit for planning permit shall not exceed five working days.

The building permit could be processed completely online, and the time limit shall not exceed five working days.

The time limit for real estate registry shall not exceed three working days. The Real Property Ownership Certificate will be delivered by mail.

Article 7 The free items for public utilities are as follows:

1. Water supply: The water connection pipe is less than 4 centimeters in diameter.

2. Water sewage: The peak wastewater flow of 50 tons a day, and the sewerage connection pipe is less than 50 centimeters in diameter.

3. Power supply: The voltage shall be below 10kv (excluding 10kv), the reporting capacity shall be less than 160kw, and the length of power line shall be less than 150 meters.

Public utilities enterprises shall be responsible for the connections of water supply, sewage and power supply.

    Neither private sector nor public utilities enterprises need to go through any administrative permit procedure.

Article 8 The Planning and Natural Resources Commission shall supervise the design quality by random checks of building drawings after the projects begins construction.

Geo-technical study and soil test shall be done by the architectural design unit. 

Quality and safety inspection shall be conducted only once for no more than one day during the construction.

Article 9 All surveying and mapping results involved in the project shall be recognized and shared among government departments.

Credit management shall be implemented for surveying and mapping units and staffs.

Article 10 The Commission of Housing and Urban-rural Development shall organize the following departments to conduct final checks of the construction project and issue On-site Notification of joint acceptance:

1. The Planning and Natural Resources Commission; 

2. The Fire Department;

3. The Market Supervision Bureau;

4. The Real Estate Registry Centre.

Connection of water and sewage services should be done simultaneously at the final check.

Article 11 Real estate tax payment and transfer registration shall be done within one day.

Online recording of real estate contracts between enterprises is canceled.

Article 12 Other types of construction projects that are subject to the implementation of the foregoing relevant measures shall be separately stipulated by relevant departments.

Article 13 These regulations shall come into force as of April 28, 2019.